Book a consultation

Insights

Site Acceptance Test Checklist for Plant Controls: From Power-On to Handover

Run a site acceptance test on a new line: a go/no-go before power-on, the FAT rerun on site, a measured ramp-up and a usable turnover. Free checklist.

Vladimir Romanov ·


Table of contents7 sections

The factory acceptance test is over, the skid is on the floor, and the electricians say they will be ready to energize on Friday. Someone has to decide whether that is true. On most projects nobody is named to decide, so power goes on when the schedule says it does.

Between the FAT and handover there are four gates, and the site acceptance test (SAT) is only one of them. A site acceptance test checklist that stops at the SAT misses the other three. The gates are a readiness decision before power-on, the SAT itself (the FAT protocol rerun on site), a ramp-up with an exit criterion, and a turnover package that maintenance can use. Most of the trouble sits at the two ends, readiness and handover, and not in the logic.

Joltek’s founder, Vladimir Romanov, led the controls scope on three production lines built in four countries and commissioned at one site for a global consumer goods manufacturer. The checklist below is built around what that kind of project needs at each gate: a named owner, one record format from FAT to SAT, and evidence that can be checked on the day.

This guide is for the plant-side project or engineering manager who is receiving the line. It covers:

  • the go or no-go that comes before power-on, with a table you can use as written;
  • what the SAT repeats from the FAT, and what it adds on site;
  • how to sort the punch list by the gate each item blocks;
  • how to set the end of ramp-up before it starts;
  • what a turnover package has to let maintenance do.

Where the FAT ends and commissioning begins is covered in what each actually covers when FAT, SAT and commissioning are compared. This post follows the same line: the SAT runs with real field devices and interfaces, usually with the process not running. Product and rate belong to commissioning.

The four gates from FAT to handoverA top to bottom diagram of the four gates between the factory acceptance test and handover, in order. Gate 1, readiness, the go or no-go before power-on: owned by the plant project or engineering manager, with the EHS lead signing the energization line; the record is the go or no-go table, each row go, no-go, or go with a written condition; the question is whether the evidence is in place, row by row, to power on. Gate 2, the site acceptance test, the FAT protocol rerun on site: owned by the plant, which signs the SAT record; the record is the SAT record in the FAT format, with tests that differ from the FAT marked; the question is whether the installed system passed the repeated protocol with real field devices and interfaces. Gate 3, ramp-up, measured with an exit criterion: owned by the operations lead and the plant project manager; the record is the exit criterion table, agreed before the first shift of ramp-up; the question is whether the line has held the agreed rate and quality for the agreed run, with every loss named. Gate 4, turnover, a package maintenance can use: owned by the plant project manager with the maintenance lead; the record is the turnover package, signed as accepted after the use tests; the question is whether a technician can trace a signal, restore a controller and find a spare without calling the integrator.1ReadinessGo or no-go beforepower-onOwnerPlant project or engineering manager. The EHS leadsigns the energization line.RecordThe go or no-go table, reviewed one row at a time.Each row is go, no-go, or go with a writtencondition.Go or no-goIs the evidence in place, row by row, to power on?2SiteacceptancetestThe FAT protocolrerun on siteOwnerThe plant, which signs the SAT record.RecordThe SAT record in the FAT format. Tests that differfrom the FAT are marked.Go or no-goDid the installed system pass the repeated protocolwith real field devices and interfaces?3Ramp-upMeasured, with anexit criterionOwnerOperations lead and plant project manager.RecordThe exit criterion table, agreed before the firstshift of ramp-up.Go or no-goHas the line held the agreed rate and quality forthe agreed run, with every loss named?4TurnoverA packagemaintenance can useOwnerPlant project manager, with the maintenance lead.RecordThe turnover package, signed as accepted after theuse tests.Go or no-goCan a technician trace a signal, restore acontroller and find a spare without calling theintegrator?Owners are Joltek's recommendation, to be adjusted to the plant's own roles.
The four gates in order, with the person who owns each one and the record that proves it passed.

What has to be true before you power on a new controls line?

Before power-on, a named person at the plant signs a go or no-go against evidence, not a percentage. The evidence is equipment built to the design, a current as-built I/O list, proven safety circuits, a lockout and energization plan, a backup of the shipped program, written procedures and trained people. OSHA’s pre-startup safety review gives the public template.

Power-on is the point where a schedule problem becomes a hazard. Until then, a missing drawing or an unverified safety circuit costs a day. After it, the same gap can cost an injury or a damaged drive, and the person who finds it is usually the one standing closest to the panel.

The fix is a single decision with a single owner. At the plant, that is the project or engineering manager, and the environmental, health and safety (EHS) lead signs the energization line. The decision is made against the table below, one row at a time, and the result for each row is go, no-go, or go with a written condition.

OSHA’s pre-startup safety review is the best public structure for this. Under 29 CFR 1910.119(i), a new facility gets a review before highly hazardous chemicals are introduced. The review confirms that construction and equipment match the design specifications, that safety, operating, maintenance and emergency procedures are in place and adequate, that a process hazard analysis was done and its recommendations resolved, and that training is complete.

That rule binds a narrow set of processes: those with a listed chemical at or above the threshold quantity, or 10,000 pounds or more of a flammable gas or flammable liquid at one location. A food or consumer goods line is usually outside it. Treat the review as a structure to borrow, not a rule that applies to you.

ItemEvidence that countsOwnerGo / no-go
Equipment built to the designWalk-down against the drawings, with deviations written and approved. Model and serial numbers of installed devices match the FAT record.Controls lead and electrical contractorGo, no-go, or go with condition
FAT defects closedEvery Critical and Major FAT item closed and verified by the plant. Minor items on the signed punch list.Plant project managerGo, no-go, or go with condition
Current as-built I/O listI/O list reconciled to the field wiring, point by point, on the day of the review.Controls leadGo, no-go, or go with condition
Safety circuits provenEmergency stops, guard interlocks and safety relays tested on the installed circuits, with the test sheet signed.EHS lead and controls leadGo, no-go, or go with condition
Lockout and energization planWritten sequence for first power-up and bump tests, with the people allowed in the area named.EHS leadGo, no-go, or go with condition
Backup of the shipped programArchive of every controller, HMI and drive configuration as shipped, stored where the plant controls it.Controls leadGo, no-go, or go with condition
Written proceduresOperating, maintenance and emergency procedures in place, even as drafts marked for update during ramp-up.Operations and maintenance leadsGo, no-go, or go with condition
Trained peopleNames of the operators and technicians who will be on shift for the SAT, with training signed.Operations leadGo, no-go, or go with condition
The decisionAll rows reviewed. Energization line signed by EHS.Plant project or engineering managerGo, no-go, or go with condition

Sources: structure from OSHA 29 CFR 1910.119(i)(2); row owners are Joltek’s recommendation, to be adjusted to the plant’s own roles.

First power-up is the highest electrical risk in the project, so name the hazard and the person who owns it, not only a clause. The hazard is energized equipment that has never been run, behind panels that people are still working near. The owner is whoever signs the energization line.

Lockout and tagout deserves a plain statement of what is and is not settled. OSHA’s 29 CFR 1910.147 covers the control of energy during servicing and maintenance, and it defines those terms to include installing and setting up equipment. It also gives an energize-to-test sequence for the moment when devices must be removed temporarily: clear tools and materials, remove employees, remove the lockout and tagout devices, energize and test, then de-energize and reapply energy control.

Construction work and normal production are outside the rule. Whether commissioning of installed production equipment falls under it depends on the work and on who is doing it. That is an interpretation, not legal advice, so confirm it with the plant’s EHS lead. Either way, the sequence is a sound way to run first power-up and bump tests.

A no-go is a normal result, not a failure. A no-go with a dated owner for each open row costs a day or two. A go that nobody checked costs the rest of the project.


What does the site acceptance test repeat from the FAT?

All of it that can be repeated, in the same record format. The SAT reruns the FAT protocol on site against real field devices, the real network and neighboring equipment, and adds the tests the shop could not run. A 2025 owner standard requires the same test-record format at FAT and SAT. Product and rate belong to commissioning.

The SAT is the FAT protocol rerun, not a new document. It uses the same test sheets, the same expected results and the same signature blocks. A tester who has seen the FAT record should be able to open the SAT record and find every test in the same place.

That is not only Joltek’s preference. Seqwater’s owner standard for control systems testing, I-SPE-STD-011, version 5, approved on 30 May 2025, is a public document from the water sector. Section 12.1(e) requires the same format of inspection and test records and test sheets at SAT as at FAT. The tests actually run at SAT can differ, and the standard says the differences shall be clearly identified in the records.

The same standard sets four rules that carry over to any plant. Defects from FAT are resolved before SAT starts. The record captures the model and serial numbers of the equipment received and installed, verified by the owner. Control systems with intermittent, unintentional or unrepeatable warnings, errors or failures are not accepted. And the SAT is a hold point: it is complete when the records and test sheets are signed and the high and medium priority defects are closed.

What the SAT adds is whatever the shop could not test. The table below pairs each FAT category with the extra work on site.

FAT test categoryWhat the SAT adds on site
Point-to-point and I/O checkoutEach point tested to the real field device, with the as-built I/O list reconciled to the wiring.
Network and communicationsThe network at real cable distances, through the real switches, with real device addressing and every connected drive and instrument online.
Interlocks and handshakesInterlocks and handshakes with neighboring equipment that was simulated at the shop, run against the actual machines.
Safety functionsEmergency stops, guard interlocks and safety relays tested on the installed circuits, not on the bench.
Backup and restoreA backup taken and a restore tested on the installed hardware, so the archive is proven on the controllers that will run the line.
Items on the FAT action listEach item the FAT assigned to the SAT, closed or carried onto the punch list with an owner and a date.
Record formatThe FAT sheets reused as they are, with every test that differs from the FAT clearly marked.

Sources: structure from Seqwater I-SPE-STD-011 version 5, sections 12.1 and 12.2; rows are Joltek’s recommendation. The FAT checklist is the first half of the same record.

Two boundary notes keep the SAT honest. ISA’s page on the ISA-105 standards says that FAT and SAT do not cover loop checks, commissioning or manufacturing execution system (MES) testing, and that IEC 62382 covers verification of electrical and instrumentation loops after installation. The parent document, IEC 62381:2024, defines requirements and checklists for FAT, SAT and site integration testing of automation systems in the process industry. Both are process-industry documents, used here by analogy.

There is also a caveat on the line itself. Seqwater’s SAT is wider than the one described here: its minimum SAT tests include dry commissioning, wet commissioning and testing during plant start-up. This post draws the line where our FAT guide draws it, with real devices and the process usually not running. The line moves with the contract, so write down which tests belong to which stage before the SAT begins.

Putting the record format into the contract is the practical step. Our post on acceptance criteria written into the scope of work covers how to require it. The record that the SAT reruns is the one in the FAT checklist for plant controls.


Which punch-list items block power-on, handover, or neither?

Sort every open item by the gate it blocks: power-on, handover, or neither. The plant verifies closure, not the contractor, and an item with no owner and no date is not on the list. This keeps the SAT from turning into a signature while open items pile up behind it.

Our FAT guide sorts defects by severity into Critical, Major and Minor. This section sorts by gate instead, because the question on site is what each open item stops. An item can be Minor by severity and still block handover if maintenance cannot work without it.

Three categories cover it. Blocks power-on: the item must close before the go or no-go is signed. Blocks handover: the item can stay open through the SAT and ramp-up, but it must close before the plant accepts the line. Can close after handover: the item is agreed, owned and dated, and it travels with the equipment. This split is the position of this post and not a vendor scheme.

Closure is verified by the plant. Seqwater’s section 14 requires defects from FAT, SAT and performance testing to be rectified and then verified by the owner, which rules out a contractor closing its own items. If the plant cannot verify a closure, the item stays open.

Keep one list for all suppliers. An item that lives in a single contractor’s spreadsheet is an item the plant cannot see, and it will surface at handover. Each item needs six fields: a description, a category, an owner, a due date, a verifier and the date it closed.

CategoryTest questionWho verifiesExample closure evidence
Blocks power-onCould energizing or running this equipment hurt a person or damage equipment while the item is open?EHS lead and controls leadRetested safety circuit with the signed test sheet; corrected wiring with the as-built I/O list updated.
Blocks handoverCould maintenance or operations not run, restore or support the line without it?Plant project manager, with the maintenance leadRestore-tested backup; reconciled as-built drawing; missing spare delivered and checked against its part number.
Can close after handoverIs the line safe, supported and accepted while the item is open, with an owner and a date?Plant project managerDated entry on the open punch list, signed by the plant, with the owner named and the due date agreed.

Sources: gate-based sorting is Joltek’s position; closure verified by the owner follows Seqwater I-SPE-STD-011 version 5, section 14(a).


How do you know ramp-up is finished?

When the line has held an agreed rate and quality for an agreed run, with every loss measured and its cause named. That is an exit criterion, not a date, and it is set before ramp-up starts. A peak-rate touch proves little; sustained capability is the test.

Ramp-up is a measured phase inside commissioning. The line runs real product, and the team counts what it makes and what it loses. It ends when the agreed criterion is met, and not before.

An honest gap belongs here. The research for this post found no traceable public benchmark for how long ramp-up takes on a manufacturing line, so there is no number worth quoting, and this guide gives none. The criterion has to be agreed locally, by the people who will own the result.

The Automation World article “Moving Beyond Checklists to Evidence-Based Commissioning of Manufacturing Startups,” by Muhammad Rafay Ikram on 28 July 2026, makes a related point: “Peak speed is not the same as sustainable production.” That is a trade article, not a primary source, so it is named here and not linked. This post adds two things to it: an exit criterion written down before the start, and an owner for every loss.

The table below is a template to fill in, not a set of values. Agree each row before the first shift of ramp-up.

CriterionValue to agreeOwner
Target rateThe rate the line must hold, in the units the plant plans against.Operations lead
Product mixWhich products count toward the run, and which do not.Operations lead
Consecutive shifts or runs at that rateThe number of shifts or runs the line must hold the rate without intervention.Plant project manager
Quality limitThe reject or defect limit that applies during the run.Quality lead
Loss categories loggedThe list of categories every stop and slowdown is logged against.Operations and maintenance leads
Each loss with an owner and a causeA named owner and a stated cause for every loss, open until it closes.Controls lead and maintenance lead

Source: Joltek’s recommendation. Fill in the middle column with the plant before ramp-up starts.

Regulated plants have a public reference for the same idea. The FDA’s 2011 process validation guidance says qualification demonstrates that utilities and equipment are suitable for their intended use, and it lists challenging the equipment under a load comparable to routine production. It does not define installation, operational or performance qualification. IQ, OQ and PQ are industry shorthand, so describe them as the plant’s validation lifecycle and follow the plant’s own quality procedures.

Seqwater gives a second public structure, in section 13 of its standard. Once water is introduced, the plant runs at a continuous rate for a smooth ramp-up to design capacity, and performance testing against the guarantees follows. The shape is the same: a sustained run first, then a test, with the criterion set in advance.

Joltek’s founder saw the same shape on three production lines built in four countries and integrated at one site. Commissioning ran for nearly three months on day and night shifts, and IQ, OQ and PQ followed. The third line was the fastest line turnaround in the site’s history. In separate line-speed work, upgrades were delivered without disrupting ongoing production, with commissioning and testing supervised under real production conditions.

For the step-by-step view of a dry run, a wet run and the ramp to an OEE target, see our post on bringing new machinery into a plant.


What belongs in a turnover package maintenance can use?

Whatever lets a technician trace a signal, restore a controller and find a spare without calling the integrator. Test each item by that use before signing: trace one input from terminal to HMI tag, restore one controller from the archive, find one spare by part number. A table of contents proves delivery, not use.

Judge the package by what maintenance can do with it, not by what is in the binder. A binder can be complete and still useless on a night shift, when a technician needs to know where a signal comes from or how to get a controller running again. The tests below are the ones to run before anyone signs.

Seqwater’s section 14 is the public list behind several rows. It names source code including credentials for protected code, programming licenses, loose spares, and the labeling of racks, I/O cards and switches. Its section 12.3 adds an “as commissioned” setpoint backup. The FAT-stage handoff list is a separate list, covered in the FAT guide, and this table does not repeat it.

ItemWhat maintenance does with itTest before signing
Signal traceFollows a signal from terminal to scan to logic to HMI tag to device when something stops working.Pick one input at random and trace it end to end with the drawings and the program.
Restore-tested backupsRebuilds a failed controller from the archive, and returns the line to its commissioned settings.Restore one controller from the archive onto a spare, and confirm an “as commissioned” setpoint backup exists.
Source code, credentials and licensesOpens, edits and downloads the program without asking the integrator for access.Open the code for a protected block with the delivered credentials, and confirm the programming licenses are in the plant’s name.
SparesReplaces a failed power supply, CPU, communication or I/O module, switch or cable.Find one spare by part number in the storeroom, and check the list against what is installed.
LabelingFinds the right rack, I/O card or switch in the cabinet at night.Walk to three labeled items and match each label to the drawing.
As-built drawingsTroubleshoots against drawings that match what was installed.Reconcile one drawing sheet against the field wiring, and note any difference.
Test recordsShows what was tested, by whom, and with what result.Confirm the FAT and SAT records are complete, signed and filed where the plant keeps them.
Training recordsShows who has been trained on which equipment.Match the names on the training records to the people on the maintenance roster.

Sources: items drawn from Seqwater I-SPE-STD-011 version 5, sections 12.3 and 14; tests are Joltek’s recommendation.

Bundled grey cables, each wrapped with a numbered yellow or green marker, terminated into a row of circuit boards inside an equipment frame
Labels are part of the turnover test. A technician on a night shift should be able to match each marker to the drawing without calling anyone.

Documents are signed as received, and receipt is not acceptance. Seqwater’s standard says so directly in section 14. Acceptance comes from running the tests above, and only then does the plant sign the package as accepted.


Where do you get the SAT and commissioning checklist?

Download the SAT and commissioning checklist, the sibling of the FAT checklist: same layout, entry criteria, owners and sign-off lines, covering all four gates. The tables above are the short version. If the plant has no hands to run the gates, Joltek can run them with your team.

The site acceptance test checklist is for the person who will sign the go or no-go and the person who will receive the line afterward. It merges the three tables in this guide with the ramp-up criterion and the punch-list fields, in one printable document. There is no email gate. Download the SAT and commissioning checklist, and adjust the owners to the roles your plant actually has.

Some plants do not have the people to spare for four gates in a row, especially when the line arrives during a production year. Joltek’s commissioning support runs the readiness gate, the SAT, the ramp-up and the turnover with your team, and leaves the records with you. If you would rather talk through the project first, book a consultation.


Frequently asked questions

How long should ramp-up to rate take?

No traceable public benchmark exists for ramp-up duration on a manufacturing line, so set the exit criterion first: rate, quality, consecutive shifts and every loss named. Then let the duration follow. Joltek’s founder saw commissioning of three lines run nearly three months on day and night shifts at one site. That is one data point, not a norm, and your line will differ.

Does passing the SAT mean the line is accepted?

No. A SAT pass means the installed system passed the repeated protocol with real field devices and interfaces. Ramp-up to the agreed rate and the turnover package still come after it. ISA also notes that FAT and SAT under IEC 62381 do not cover loop checks or commissioning, so plan for those separately and write down where the contract draws each line.

Do OSHA’s pre-startup safety review rules apply to my line?

Only if the process falls under 29 CFR 1910.119, which means a listed chemical at or above its threshold quantity, or 10,000 pounds or more of certain flammable gases or liquids at one location. Most food and consumer goods lines are outside it. Its four review items are still a sound go or no-go structure: design conformance, procedures, hazard review and training.

Is lockout/tagout required when commissioning new equipment?

OSHA’s 1910.147 covers servicing and maintenance, and it defines those terms to include installing and setting up equipment. It gives an energize-to-test sequence for when devices must be removed temporarily. It excludes construction work and normal production. How it applies to your activity depends on the work and who does it, so confirm with your EHS lead. This is not legal advice.

What goes in a SAT test record?

The same format as the FAT record: the test, the expected result, the actual result, pass or fail, who witnessed it and the date. Add the model and serial numbers of what was received and installed. Tests that differ from the FAT are clearly marked as different, and the plant signs the record. Using one format at both stages lets the SAT read as a rerun.

References and further reading

  1. 29 CFR 1910.119, Process safety management of highly hazardous chemicals · U.S. Occupational Safety and Health AdministrationParagraph (i) is the pre-startup safety review.
  2. 29 CFR 1910.147, The control of hazardous energy (lockout/tagout) · U.S. Occupational Safety and Health AdministrationParagraph (f)(1) gives the energize-to-test sequence.
  3. Control Systems Testing, I-SPE-STD-011, document SPE-00360, version 5 (approved 30 May 2025) · SeqwaterA public water-sector owner standard. Sections 12, 13 and 14 cover SAT, ramp-up and handover.
  4. IEC 62381:2024, Automation systems in the process industry. Factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT) · International Electrotechnical CommissionCatalogue page. The standard itself is paywalled.
  5. ISA-105 standards · International Society of AutomationThe scope note on FAT, SAT and loop checks.
  6. Process Validation: General Principles and Practices (January 2011) · U.S. Food and Drug AdministrationGuidance for industry.

← All insights

Have a project that needs technical ownership?

Send us the situation. If it is not something we should take on, we will say so.

The Plant-Side Brief

The weekly brief for the people who own a plant’s control systems.

One email every Wednesday for engineering and operations leaders responsible for controls, SCADA, MES and OT networks. Skim the top in two minutes; read the Deep Dive when you have fifteen.

  • One modernization problem, worked through to cost, risk and a schedule you can defend. The Deep Dive.
  • End-of-support dates before they reach your plant Windows, servers, controllers and HMI software. Lifecycle Watch.
  • A checklist your engineers can run that week not a framework to admire. Field Kit.
  • Every number sourced, no vendor agenda we are paid by plants, never by vendors.